Although, it could seems that Public
Procurement Law adjusts so called „in-house“ exception, which entitles
contracting authority to not act under a regime of law quite unequivocally, in
this case, in practice is not so clear. We can demonstrate it on actual
decision of the Office for the Protection of Competition
in case of town Dobříš.[1]
So, it is appropriate to summarize conditions for in-house exception regard to
this decision.
In-house exception
In house exception in this article is vertical
cooperation according to Section 11 of Public Procurement Law (“Law”), which
defines that award of public contract is not a contract concluded between the
contracting authority and another legal person as the economic operator shall not
be considered the award of a public contract.
For a vertical cooperation have to be concurrently
fulfilled these conditions
- the contracting authority itself or in joint cooperation with other contracting authorities
exercises over such person a control which is similar to that which it
exercises over its own departments,
- there is no capital participation of another
person in the controlled person
- more than 80 % of the activities of the
controlled person are carried out in the performance of tasks entrusted to it
by the controlling contracting authority (or controlling contracting
authorities or by other legal persons controlled by that controlling contracting
authority (or controlling contracting authorities) as its own departments).
Some aspects of in-house exception
Before we start analysing particular conditions
of in-house exception, it is important to point out that conditions of vertical
cooperation is necessary to perceive restrictively and the contracting
authority who decides to not conclude a contract to not act under the Law and in-house
exception, has to be able to prove fulfilling of all legal conditions.[2]
Before application of the in-house exception is also possible to recommend
contractual authorities to make legal analyse that they fulfil all conditions
for application and that they have all documents to prove it.
“The control which is similar to that which it
exercises over its own departments”
The meaning of “the control which is similar
to that which it exercises over its own departments” is written in the
Section 11 subsection 2 of the Law, it means that it exercises
a decisive influence over both strategic objectives and significant decisions
of the controlled legal person (simultaneously). It is a different type of
an influence than the one in the Corporations Act, the Law demands that the
control is de facto (contrary, in Corporations Act is just about the
possibility to exercise influence). According to specialised literature[3]
is necessary this rule of interpretation in Section 11,
Subsection 2 of the Law take as rebuttable presumption.
“In joint cooperation with
other contracting authorities exercises over such person a control”
What does it mean, that economic operator is
controlled by contracting authority in joint cooperation with other contracting
authorities is more precisely written in Section 11 subsection 3 of the Law. The
decision-making body, which is mentioned in section 11 subsection 3 of the Law
is the one that de facto exercises a decisive influence over both strategic
objectives and significant decisions of the controlled legal person, so mostly
it is governing body which does business management. However, in particular
cases, this body could be also controlling body (mostly with governing body) or
other bodies of an economic operator.
“More than 80 % of the activities of the
controlled person are carried out in the performance of tasks entrusted to it”
The average turnover is the key for
determination of percentage activities according to Section 11 subsection 1
paragraph c) of the Law, if the activity which is the subject-matter of the
contract is fully paid by its recipients. Where such turnover may not be
determined then, with regard to vertical cooperation, total costs of such a
legal person shall be used as the grounds for calculation. According to of the
Office for the Protection of Competition which is mentioned at the beginning of
the article (“Decision”) and specialised literature it is necessary to determine
the turnover on the base of profit and loss account
According to Czech and European jurisprudence[4],
between activities of the controlled legal person which were assigned by
controlling contracting authority, it is necessary to include all assigned
activities, which were assigned by the
controlling contracting authority regardless who is the real receiver of this
activities, i.e. also activities assigned for legal persons controlled by the
contract authority (for example subsidiary of the contracting authority). According
to the Decision, it doesn't include activities which were
assigned to the economic operator by the contracting authority in favour of
other contracting authorities who don't control the economic operator.
Percentage of activities is calculated
according to Section 13 subsection 2 of the Law as the sum of the 3 years
preceding the accounting period in which the contract was awarded.[5]
According to the Decision is decisive the average value of 3 subsequent period,
so i tis not necessary to fulfil rate of conditions individually each year. If
happened a situation because of which the indicator of the percentage of
activities in the 3 years preceding the accounting period is not objectively
relevant, i.e. the economic operator started the activity later or his activity
was reorganised it is not necessary to assess the percentage of activities as
the sum of 3 years preceding, it tis enough that the conditions were credibly
reached, especially based on plans of activities.
The Decision of the Office for the Protection
of Competition was about the problem of percentage of activities according to
Section 11 subsection 1 paragraph c) of the Law. The Office for the Protection
of Competition judged the situation (in a simplified way) when town Dobříš
awarded the in-house exception contract with the subject who didn't fulfil the condition of the percentage
of activities in the 3 years preceding the accounting period, the town Dobříš
know this problem and planed to solve it in the future by reorganisation of
this economic operator (but in the time of conclusion of a contract the town
did not even start the reorganisation or decided about it).
The Office for the Protection of Competition
said, that this procedure is inadmissible, because the precondition for the
calculation of the percentage of the activities 3 years not preceding the
accounting period, but 3 future years of activities is the real reorganisation
of the economic operator, not just planning of doing it. According to the
Office for the Protection of Competition, in the time of award of contract, has
to exist the objective reason why the calculation of the percentage of
activities according to 3 years preceding would not be relevant.
Conclusion
In conclusion, we would like to sum up the above
– even the in-house exception, which at first sight seems clear and easy
to applicate, hides some ambiguousness in interpretation and risks for the
contracting authority which can be caused by bad interpretation and
application. We recommend to contracting authorities like first, to properly
consider if the exception can be used and store all documents, which they can
use as evidence that they fulfil conditions.
[1] Decision, file No. 21251/2020/322/DJa (město Dobříš), 13.7.2020
[3]
§ 11 [Vertikální
spolupráce]. In: DVOŘÁK, David, MACHUREK, Tomáš, NOVOTNÝ, Petr, ŠEBESTA, Milan,
KOSMÁKOVÁ, Darja, KRUMBHOLC, Filip, MAREŠ, David, BOROŠOVÁ, Hana, GALÁŘ, Jan,
GULDOVÁ, Denisa, JEŘÁBEK, Jakub, LÁTAL, Martin, LELITOVSKÁ, Lenka, MACHÁLKOVÁ,
Michaela, MÜLLER, Veronika, PODOLOVÁ, Libuše. Zákon o zadávání veřejných
zakázek. 1. vydání. Praha: Nakladatelství C. H. Beck, 2017, s. 69.)
[4] Decision CJEU, 11. 5. 2006, C-340/04, Carbotermo SpA a Consorzio Alisei proti Comune di Busto Arsizio a AGESP SpA; Decision of Regional Court in Brno. 22. 9. 2017, file No. 31Af 5/2016 - 79
[5] The finnancial year when the contract was concluded is not counted